Now the drain boxes are in place and leveled. The new ridgid connecting drain pipes...
6/6/11 3:31 PM
50
The east roof and patio drain will discharge in to the backyard here.
6/6/11 3:32 PM
51
Fortunately, the wood rot was limited to the trim board. The rest is in pretty good...
6/8/11 7:32 AM
52
The patio flagstone arrived this morning. Some heavy lifting ahead.
6/8/11 8:45 AM
53
Austin is warming up by mixing concrete. (Ha- it's 96 degrees today.)
6/8/11 8:47 AM
54
Austin poured the base for the east patio doors.
6/8/11 10:28 AM
55
The base for the north patio doors takes shape.
6/8/11 10:31 AM
56
Our load of stone dust arrives. This will be the base material for the patio flagstones.
6/8/11 2:23 PM