| DIV | SEC | Owner | Bidder/Builder |
| 01 General Requirements | 10 | . | Permits & Fees - (At owner's expense) obtain zoning, building & water permits. (Dombwaiter State permit to be obtained by DW dealer.) |
| 12 | . | Arrange testing & inspections by agencies. | |
| 14 | Remove furniture. | . | |
| 17 | . | Secure & pay for temporary utilities. | |
| 29 | . | Supply all warrantees & manuals for equipment. | |
| 31 | . | Provide copy of C.O. (Arch to provide ""as built"" dwgs for C.O. at owner's expense.) | |
| 32 | . | Repair & replacement for one year after C.O. | |
| 02 Site Work | 01 | Pay surveyor for benchmark & corner stakes, site plan (as built) & flood certificate. | . |
| 02 | Remove (salvage) equipment before demolition. | Clear lot. Demolish house. Remove Freon. | |
| 09 | Pay town to upgrade water service lateral to curb box to 1". Pay for town to replace sewer lateral if necessary. | Coordinate processing & scheduling of water & sewer. | |
| 10 | Pay for new gas line & meter. | Coordinate new gas. | |
| 13 | Pay for new 200 amp underground electrical service, phone & Comcast. | Coordinate new electrical, phone & cable. | |
| 28 | Determine what to do with curb. | Provide alternate price for new curb installed to town standards. | |
| 29 | Determine area to be paved. Hire separate contractor. | Coordinate rough grading and schedule with paving contractor. | |
| 33 | Provide new trash corral. | Don't wreck old one (yet). | |
| 03 Concrete | 09 | Seal foyer & storage room slabs (yes, really). | . |
| 10 | Determine what to do with curb. | Provide alternate price for new curb installed to town standards. | |
| 04 Masonry | 09 | . | Aluminum termite shield to be Cu? None? |
| 05 Metals | . | . | . |
| 06 Wood & Plastics | . | . | . |
| 07 Thermal & Moisture Protections | 21 | Wood Trellis or Lattice - Provide design for ground floor arch panels - removable fence pattern, unfinished 1X WRC panels. | . |
| 08 Doors & Windows | 02 | External glass doors- walk thru rough frame w/ GC to review before ordering. | Review external glass doors with Arch before ordering. |
| 08 | Determine overhead garage doors. | . | |
| 10 | Clad wood windows- walk thru rough frame w/ GC to review before ordering. | Review clad wood windows with Arch before ordering. | |
| 09 Finishes | 07 | Carpet - Carpet & installation to be under separate contract. | . |
| 09 | Paint & Staining - Need to distill this item. | . | |
| 10 Specialties | 09 | House number (""two"") to be provided. | . |
| 13 | Air conditioner condenser covers (canvas) under separate contract. | . | |
| 16 | Supply & install all closet & laundry shelving. | . | |
| 17 | Bath Accessories - Tile-in accessories supplied by owner. | . | |
| 21 | Supply two medicine cabinets . Provide rough opening dimensions to GC. | . | |
| 23 | Supply weathervane. | . | |
| 11 Equipment | 01 | Cental Vacuum - Supply & install. | . |
| 05 | Modify outdoor Webber gas grille for natural gas. | . | |
| 12 Furnishings | 02 | Supply kitchen and bath cabinets and countertops. Counters installation under separate contract. | Install kitchen and bath cabinets. |
| 03 | Solid surface material counters and integral lav bowls and installation under separate contract. | . | |
| 13 Special Construction | . | . | . |
| 14 Conveying Systems | 01 | Dumbwaiter - Supplied by "manufacturer" (means owner?) | Install dumbwaiter (doesn't vendor rep do this?) |
| 15 Mechanical | 16 | Plumbing Fixtures - Faucets supplied by owner. Undermount sink (kitchen) & integral bowl lav tops including installation are under separate contract. Review fixture model numbers on plumbing schedule before orders are placed. | Faucets installed by GC/plumber. |
| 26 | Duct work - Do walk-thru before rough rough-in. | . | |
| 28 | Provide two plug-in dehumidifiers to ground floor. Determine locations for GC. | . | |
| 29 | A.C./heat registers & grilles - Do walk-thru review before rough-in. Determine source of plastic supply registers. | Atlanta Supply for registers | |
| 16 Electrical | 02 | Pay for underground 200 amp service and meter. | . |
| 04 | Do walk-thru before rough wiring. | . | |
| 07 | Provide all non-specified lighting fixture and fans. | Provide specified lighting fixtures. | |
| 09 | Pre-wire and finish telephone & cable. | . | |
| 14 | Low-voltage wiring - Run 1-1/2" (?) conduit from 1st floor to 2nd floor. (Should be utility room to attic space?) | . |